Under normal conditions using an ordinary cement, the period of removal of the form work, is
A.
7 days for beam soffits
✓
✗
B.
14 days for bottom slabs of spans 4.6 m and more
✓
✗
C.
21 days for bottom beams over 6 m spans
✓
✗
D.
All of these
✓
✗